DRR activities under implementation

September 10, 2026

    Under Result Area I: Disaster Risk Reduction (DRR) Implementation (Output 1: DRR Interventions), activities are underway across two target Weredas:

    In Uba Debre Tsehay (Focal), three key interventions are planned:

    • Construction of a comprehensive human health post in Galada Kebele has reached 50% implementation status; substructure works are completed, and superstructure construction is ongoing to benefit 7,018 male and 6,813 female community members.
    • Drinking water development in Zaba Kebele is at 60% completion, having finalized the reservoir, water points, and spring capping, with pipeline extension remaining; this scheme targets 10,038 male and 9,556 female beneficiaries.
    • A livelihood (LH) improvement activity in Guassa Kebele targets 3,461 male and 3,438 female beneficiaries (specific activities accomplished to date and implementation status are not indicated in the table).

    In Abala Abaya (Focal), planned interventions include:

    • Construction of two animal health posts in Abaya Gurucho and Abaya Longena Kebeles is at the initiation stage, with site selection completed, the bid announced, and the sale of bid documents ongoing, targeting 1,820 male and 1,900 female beneficiaries.
    • Drinking water development in Sippa Kebele (sourced from Shoita) is also at the initiation stage, with sites selected, the bid announced, and bid document sales ongoing to serve 9,611 male and 10,417 female beneficiaries.
    • A livelihood (LH) improvement activity targets 10,166 male and 10,696 female beneficiaries, though its specific implementation site, progress status, and activities to date are unrecorded in the source table.